Warwick Hospital

Are you looking for an experienced construction and civil engineering company
for your next project? Get in touch and let us know what your requirements are.

contact us

Alto Construct were appointed to carry out the groundworks package for the construction of a new ward and retail block at Warwick Hospital.

The works comprised of the following:

  • Construction of a large reinforced concrete slab 2000m2 for the sitting of modular units
  • Construction of all surface water and foul water drainage systems
  • Installation of an attenuation tank and hydro brake flow control manhole for surface water control
  • Construction of external reinforced concrete plant slabs for associated plant and equipment for the new ward
  • Construction of new external works including footpaths, block paving plus  hard and soft landscaping

Quick Facts

Client:

Noviniti

Programme:

20 weeks

Value:

£850,000