New Hall Road Distribution Centre – Groundworks

Are you looking for an experienced construction and civil engineering company
for your next project? Get in touch and let us know what your requirements are.

contact us

Alto were appointed as groundworks contractor on the development of a large distribution centre in Sheffield. The project comprised of:

  • All groundworks for the scheme including construction of all foundations, earthworks to create the development platform
  • Installation of all surface and foul water drainage system including large attenuation tanks
  • Construction of surface water outfall into the River Don
  • Creation of 150 000sq ft reinforced concrete external yard and dock levellers
  • Construction of ground floor reinforced concrete slab
  • All external works and landscaping

Quick Facts

Client:

UC Build

Programme:

40 weeks

Value:

£2.5 million