Alto was appointed by Galliford Try on the construction of a large new academy school in Bolton.

The works involved:

  • 75000m3 of Bulk Earthworks to create level platform for the academy and the sports/MUGA pitches.
  • Foundations to main and ancillary buildings
  • Removal of excessively soft material and backfilling with imported clean aggregate, approximately 22,000m3
  • Installation of 2 large attenuation tanks
  • Installation of all Surface Water and Foul Water
  • Installation of Gas Membrane
  • Construction of all ground floor slabs
  • Construction of all external works including landscaping
  • Construction of a large Surface Water culvert (largest Precast units in UK at that time, Video included) and subsequent road construction.
  • Section 278 works to form new entrance over culvert.
  • Drainage Works related to underside of MUGA and new pitches.

Quick Facts

Client:

Galliford Try

Programme:

45 weeks

Value:

£3.96m