Alto Construct were awarded the civils and groundworks package for the construction of a new A&E facility at the CCED Hospital in Chester. This was an extremely challenging project due to working within a live hospital site. This project comprised of:
- Installation of pad foundations and ground beams.
- Diversion of foul sewer and installation of new drainage system.
- Construction of a reinforced concrete slab and concrete roof for the new facility.
- ll external works and external finishes.
Quick Facts
Client:
Galliford Try
Completion:
January
Programme:
4 months
Value Range:
£320,000