Alto were employed as a sub-contractor for the construction of the new extension block to the existing Bradford Maternity Unit.
Site had numerous challenges and constraints including a live hospital environment, numerous chartered and unchartered services and challenging logistics.
Works included:
- Construction of foundations
- Construction of surface and foul water drainage
- New ground floor, reinforced concrete slab
- Construction of RC retaining walls and to accommodate level changes for access ramps and staircase
- Works to the existing highway
- Construction of all external works, paving and landscaping.
Quick Facts
Client:
Morgan Sindall
Programme:
12 weeks
Value:
£350,000